Abstract
This paper provides general considerations for determining
working clearances required to carry out live line barehand
insulator change out work on energized power lines operating at
345 kV and above. It is intended to focus on a limited number of
procedures and will only address one common structure configuration.
This paper is intended to be used in conjunction with IEEE
516 Guide for Maintenance Methods on Energized Power Lines.
Keywords
bare hand work , glassinsulators , air gap , Aerial lift methods , live line work , porcelain insulators.