• Title of article

    A Reliability-Based Approach to Transmission Maintenance Planning and Its Application in BC Hydro System

  • Author/Authors

    W. Li and J. Korczynski، نويسنده ,

  • Issue Information
    روزنامه با شماره پیاپی سال 2004
  • Pages
    6
  • From page
    303
  • To page
    308
  • Abstract
    This paper presents a reliability-based method for transmission maintenance planning. A quantified impact assessment of the planned outage on operation reliability of the whole transmission system is a main feature of the proposed method. This reliability centered maintenance (RCM) approach for transmission systems provides not only the lowest risk maintenance schedule but also the most reliable operation mode for the planned outage. Another feature of the method is ease of incorporation into the existing traditional transmission maintenance procedure. A time-shift-based Monte Carlo simulation technique and a linear programming optimization model are used to perform reliability evaluation of the transmission system with planned outage(s). An example for the planned replacement of a 230-kV cable in the BC Hydro North Metro system has been given to demonstrate a practical application of the proposed procedure and the method.
  • Keywords
    transmission planned outage , transmissionmaintenance , transmission reliability. , Reliability centered maintenance
  • Journal title
    IEEE TRANSACTIONS ON POWER DELIVERY
  • Serial Year
    2004
  • Journal title
    IEEE TRANSACTIONS ON POWER DELIVERY
  • Record number