Title of article
Application of chronological load modeling in composite reliability worth evaluation
Author/Authors
J.C.O. Mello، نويسنده , , M.V.F. Pereira، نويسنده , , A.M. Leite da Silva، نويسنده , , A.C.G. Melo، نويسنده ,
Issue Information
روزنامه با شماره پیاپی سال 1997
Pages
8
From page
167
To page
174
Abstract
This work describes the application of pseudo-sequential Monte Carlo simulation to the composite generation—transmission reliability evaluation of the Brazilian South-Southeast system using chronological load modeling. The resulting reliability indices, in particular the loss of load cost (LOLC), were compared with those produced by a sequential Monte Carlo scheme with chronological load model and by a non-sequential Monte Carlo simulation scheme using a multistate Markov load model. It is shown that the pseudo-sequential approach produced the same indices as the sequential approach, with a substantial reduction of computational effort. Those results were in turn quite different from the non-sequential Monte Carlo scheme, thus confirming the importance of an accurate load modeling.
Keywords
Monte-Carlo simulation , Composite generation—transmission systems , Chronological load model , Interruption costs
Journal title
Electric Power Systems Research
Serial Year
1997
Journal title
Electric Power Systems Research
Record number
415404
Link To Document