Title of article
Job shop scheduling heuristics for sequence dependent setups
Author/Authors
Chinyao Low، نويسنده ,
Issue Information
دوماهنامه با شماره پیاپی سال 1995
Pages
5
From page
279
To page
283
Abstract
In this paper we develop a more realistic algorithm which addresses the job shop scheduling problem with sequence dependent setup times, and some complex constraints such as multiple machines, multiple resources, and alternate routes; then, we evaluate the performance of the algorithm relative to the performance criteria used in the real world shops. To illustrate the potential impact of addressed problem, we simulate the scheduling jobs using three different approaches under a variety of conditions. Experimental designs are used to find the difference among these approaches, and to justify the value of the more realistic approach.
Journal title
Computers & Industrial Engineering
Serial Year
1995
Journal title
Computers & Industrial Engineering
Record number
924354