Title of article :
Flow-time performance of modified scheduling heuristics in a dynamic rescheduling environment
Author/Authors :
Yi-Ching Eric Li، نويسنده , , Wade H. Shaw Jr.، نويسنده , , Louis A. Martin-Vega، نويسنده ,
Issue Information :
ماهنامه با شماره پیاپی سال 1996
Pages :
4
From page :
213
To page :
216
Abstract :
A generic, modular simulation model was constructed using the SLAM II discrete event modeling language to investigate the flowtime performance of a job shop. The findings of earlier research using conventional scheduling heuristics were confirmed and used to validate the design of revised AWINQ and MST heuristics. These heuristics were reformulated to take into account the state of the entire job shop at each rescheduling opportunity. Simulation results indicate that the revised heuristics perform better than the conventional SPT heuristic when job load is moderate. At high loads, the SPT rule was the preferred heuristic.
Keywords :
Jobshop , flowtime , Scheduling , simulation , dynamic scheduling , Heuristic
Journal title :
Computers & Industrial Engineering
Serial Year :
1996
Journal title :
Computers & Industrial Engineering
Record number :
924535
Link To Document :
بازگشت