Title of article
Series production in a basic re-entrant shop to minimize makespan or total flow time
Author/Authors
Feng Chu a، نويسنده , , *، نويسنده , , Chengbin Chu b، نويسنده , , Caroline Desprez a، نويسنده , , c، نويسنده ,
Issue Information
ماهنامه با شماره پیاپی سال 2010
Pages
12
From page
257
To page
268
Abstract
This paper addresses a real life shop scheduling problem in a manufacturing company. In this problem, a
set of n identical jobs are to be processed on two machines. Every job visits one of the machines more
than once. This is therefore a re-entrant shop. Due to the fact that the jobs are identical, the decision version
of this problem is even not in the class NP. We give an optimal schedule to minimize the makespan.
Since the total flow time depends on the relations between the processing times, we decompose this
problem into sub-problems according to the relations between the processing times. We prove various
properties of optimal solutions and, based on these properties, we provide an optimal solution for all
the sub-problems except one of them. For the sole remaining sub-problem, we prove a dominance property
which allows to consider a part of schedules to find an optimal one.
Keywords
Total flow time , Scheduling , Series production , Re-entrant shop , Makespan
Journal title
Computers & Industrial Engineering
Serial Year
2010
Journal title
Computers & Industrial Engineering
Record number
925844
Link To Document