Title of article :
Coupled-task scheduling on a single machine subject to a fixed-job-sequence q
Author/Authors :
F.J. Hwang، نويسنده , , Bertrand M.T. Lin، نويسنده ,
Issue Information :
ماهنامه با شماره پیاپی سال 2011
Pages :
9
From page :
690
To page :
698
Abstract :
This paper investigates single-machine coupled-task scheduling where each job has two tasks separated by an exact delay. The objective of this study is to schedule the tasks to minimize the makespan subject to a given job sequence. We introduce several intriguing properties of the fixed-job-sequence problem under study. While the complexity status of the studied problem remains open, an O(n2) algorithm is proposed to construct a feasible schedule attaining the minimum makespan for a given permutation of 2n tasks abiding by the fixed-job-sequence constraint. We investigate several polynomially solvable cases of the fixed-job-sequence problem and present a complexity graph of the problem.
Keywords :
Makespan , Coupled tasks , Exact delays , Fixed-job-sequence
Journal title :
Computers & Industrial Engineering
Serial Year :
2011
Journal title :
Computers & Industrial Engineering
Record number :
926091