• Title of article

    Scheduling of parts and robot activities in a two machine robotic cell

  • Author/Authors

    Y. P. Anej، نويسنده , , H. Kamoun، نويسنده ,

  • Issue Information
    دوهفته نامه با شماره پیاپی سال 1999
  • Pages
    16
  • From page
    297
  • To page
    312
  • Abstract
    We consider a scheduling problem arising in a two machine flexible robotic cell that repetitively produces parts of different types. We consider the two decisions that need to be made simultaneously: finding the robot move cycle, and finding the input part sequence. The objective is to maximize the throughput rate of the cell subject to the condition that parts are to be produced in proportion of their demand. The problem can be formulated as a special kind of traveling salesman problem. An O(n4) time algorithm which solves this problem optimally has been provided in Hall et al. (1997). In this paper, we extend their work and provide an algorithm of complexity View the MathML source.
  • Keywords
    Robotic cell , Travelling salesman problem , Algorithm , Manufacturing , Deterministic scheduling
  • Journal title
    Computers and Operations Research
  • Serial Year
    1999
  • Journal title
    Computers and Operations Research
  • Record number

    927004