• Title of article

    Hierarchical minimization of completion time variance and makespan in jobshops

  • Author/Authors

    Viswanath Kumar Ganesan، نويسنده , , Appa Iyer Sivakumar، نويسنده , , G. Srinivasan، نويسنده ,

  • Issue Information
    ماهنامه با شماره پیاپی سال 2006
  • Pages
    23
  • From page
    1345
  • To page
    1367
  • Abstract
    This paper addresses the problem of minimizing makespan for a given set of n jobs to be processed on each of m machines in a static jobshop, subject to the minimum completion time variance (CTV). A lower bound on CTV is developed for the static jobshop problem. A backward scheduling approach is proposed using the observations on the development of lower bound for hierarchical minimization of CTV and makespan. A lower bound on makespan subject to minimum CTV is also presented for this problem. Finally, we present two simulated annealing heuristic approaches using the concepts of forward and backward scheduling. Their performances are compared against each other through the use of the lower bounds established in this work. The simulated annealing heuristic based on backward scheduling is shown to perform well by evaluating the developed heuristics on 82 jobshop problems taken from literature.
  • Keywords
    Performance evaluation , Mean value analysis , Yield , Machine Failure , Re-entrant manufacturing system
  • Journal title
    Computers and Operations Research
  • Serial Year
    2006
  • Journal title
    Computers and Operations Research
  • Record number