Abstract
This paper describes the step-by-step process of repair and upgrade which restored a damaged 40-year-old 3.5 MW hydroelectric power plant to service after nearly six years of downtime. Detailed information is provided on the approach to the restoration work taken by the Massachusetts Water Resources Authority (USA). Hidden damage, outdated turbogenerator protective relaying, and inadequate surge protection are discussed
Keywords
hydroelectric power stations; machine protection; maintenance engineering; project engineering; relay protection; surge protection; turbogenerators; 3.5 MW; USA; damage; hydroelectric power plant; maintenance project; protective relaying; repair; restoration; surge protection; upgrade; Coils; Lightning; Power generation; Protective relaying; Reservoirs; Stator cores; Substations; Testing; Turbines; Water resources;
fLanguage
English
Journal_Title
Energy Conversion, IEEE Transactions on
Publisher
ieee
ISSN
0885-8969
Type
jour
DOI
10.1109/60.260974
Filename
260974
Link To Document