• DocumentCode
    1044767
  • Title

    Multihoist Cyclic Scheduling With Fixed Processing and Transfer Times

  • Author

    Jiang, Yun ; Liu, Jiyin

  • Author_Institution
    Bilkent Univ., Ankara
  • Volume
    4
  • Issue
    3
  • fYear
    2007
  • fDate
    7/1/2007 12:00:00 AM
  • Firstpage
    435
  • Lastpage
    450
  • Abstract
    In this paper, we study the no-wait multihoist cyclic scheduling problem, in which the processing times in the tanks and the transfer times between tanks are constant parameters, and develop a polynomial optimal solution to minimize the production cycle length. We first analyze the problem with a fixed cycle length and identify a group of hoist assignment constraints based on the positions of and the relationships among the part moves in the cycle. We show that the feasibility of the hoist scheduling problem with fixed cycle length is consistent with the feasibility of this group of constraints which can be solved efficiently. We then identify all of the special values of the cycle length at which the feasibility property of the problem may change. Finally, the whole problem is solved optimally by considering the fixed-cycle-length problems at these special values. Note to Practitioners-Automated electroplating lines are commonly used in the production of many products, such as printed-circuit boards. The productivity of these systems depends heavily on effective scheduling of the material handling hoists that move the products between the processing tanks. This paper studies the hoist scheduling problem in systems where the processing times in the tanks and the intertank move times are fixed parameters. An efficient optimal algorithm is developed to solve the problem with any number of hoists. The resulting schedule can be programmed as programmable logic controller codes to directly control the hoist operations. The algorithm can also be used to develop heuristic solutions for multihoist scheduling in systems where the processing times may vary in given intervals.
  • Keywords
    electroplating; hoists; optimisation; scheduling; fixed processing; fixed-cycle-length problems; hoist assignment constraints; hoist scheduling problem; multihoist cyclic scheduling; polynomial optimal solution; processing times; production cycle length; transfer times; Automation; Chemical products; Chemical technology; Materials handling; Polynomials; Production systems; Productivity; Programmable control; Scheduling algorithm; Hoist scheduling; multiple hoists; no-wait; optimization;
  • fLanguage
    English
  • Journal_Title
    Automation Science and Engineering, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    1545-5955
  • Type

    jour

  • DOI
    10.1109/TASE.2006.884057
  • Filename
    4266817