DocumentCode
1049635
Title
Placement of Synchronized Measurements for Power System Observability
Author
Chakrabarti, Saikat ; Kyriakides, Elias ; Eliades, Demetrios G.
Author_Institution
Univ. of Cyprus, Nicosia
Volume
24
Issue
1
fYear
2009
Firstpage
12
Lastpage
19
Abstract
This paper presents a method for the use of synchronized measurements for complete observability of a power system. The placement of phasor measurement units (PMUs), utilizing time-synchronized measurements of voltage and current phasors, is studied in this paper. An integer quadratic programming approach is used to minimize the total number of PMUs required, and to maximize the measurement redundancy at the power system buses. Existing conventional measurements can also be accommodated in the proposed PMU placement method. Complete observability of the system is ensured under normal operating conditions as well as under the outage of a single transmission line or a single PMU. Simulation results on the IEEE 14-bus, 30-bus, 57-bus, and 118-bus test systems as well as on a 298-bus test system are presented in this paper.
Keywords
integer programming; power system measurement; quadratic programming; synchronization; IEEE bus test system; PMU; integer quadratic programming approach; phasor measurement unit; power system bus; power system measurement; single transmission line; time-synchronized measurement; Current measurement; Observability; Phasor measurement units; Power measurement; Power system measurements; Power system simulation; Quadratic programming; System testing; Transmission line measurements; Voltage measurement; Integer quadratic programming; observability; optimal placement; phasor measurement units (PMUs); synchronized measurements;
fLanguage
English
Journal_Title
Power Delivery, IEEE Transactions on
Publisher
ieee
ISSN
0885-8977
Type
jour
DOI
10.1109/TPWRD.2008.2008430
Filename
4729806
Link To Document