Title :
The Fenno-Skan HVDC link commissioning
Author :
Nyman, A. ; Jääskeläinen, K. ; Vaitomaa, M. ; Jansson, B. ; Danielsson, K.-G.
Author_Institution :
Swedish State Power Board, Vallingby, Sweden
fDate :
1/1/1994 12:00:00 AM
Abstract :
The commissioning of the Fenno-Skan HVDC link between Finland and Sweden, with the longest submarine DC cable in the world, is described. The main pre-commissioning activities, important for an efficient commissioning, are discussed together with time schedules and suitable organisation forms. The procedures to test special control features, such as subsynchronous oscillation (SSO) damping control are presented. The full scale network interaction tests which are an important part of the commissioning are also discussed. These tests succeeded very well and provided a lot of information about the system behaviour for future operation and planning purposes
Keywords :
DC power transmission; damping; oscillations; power cables; submarine cables; Fenno-Skan HVDC link commissioning; Finland; Sweden; organisation forms; pre-commissioning activities; submarine DC cable; subsynchronous oscillation damping control; time schedules; HVDC transmission; Power cables; Power system interconnection; Power system planning; Power system reliability; Power system stability; Power systems; Power transmission; Testing; Underwater vehicles;
Journal_Title :
Power Delivery, IEEE Transactions on