Abstract
The real-time interface requirements of a large hydroelectric power plant with its regional load dispatch office are described. The operative arrangement, interfacing functions, annual and weekly generation schedule, and unit commitment are discussed. Automatic generation control, automatic bus voltage, river flow control, and operating conditions are discussed. All the functions were implemented for the Guri Hydroelectric Project in Venezuela, with total generating capacity of 10000 MW. Operation management functions are all handled by the Guri Computer Control System
Keywords
hydroelectric power stations; load dispatching; power engineering computing; 10000 MW; Guri Computer Control System; Guri Hydroelectric Project; Venezuela; automatic bus voltage; automatic generation control; hydroelectric power plant; operating conditions; operation management functions; real-time interface; regional load dispatch office; river flow control; unit commitment; Automatic generation control; Automatic voltage control; Computer interfaces; Computer networks; Control systems; Data flow computing; Power engineering and energy; Power generation; Processor scheduling; Standby generators;
fLanguage
English
Journal_Title
Energy Conversion, IEEE Transactions on
Publisher
ieee
ISSN
0885-8969
Type
jour
DOI
10.1109/60.107225
Filename
107225
Link To Document