Abstract :
To facilitate uprating of HV substations, a reexamination is made of line-to-line insulation design criteria. The basis for existing practices and the principles of line-to-line lightning surge overvoltage stresses are reviewed. Results of a digital study for a realistic substation are presented. The conclusions show that the line-to-line stresses, as limited by surge arresters, are substantially higher than line-to-ground stresses. This represents increased requirements as compared to existing standards. However, due to the low protective levels of modern arresters, substantial reduction of line-to-line clearances is still feasible
Keywords :
lightning protection; overvoltage; substations; surge protection; HV substations; lightning surge overvoltage stresses; line-to-line insulation design criteria; phase-to-phase clearances; surge arresters; Arresters; Flashover; Insulation; Lightning; Marketing and sales; Senior members; Stress; Substations; Surge protection; Voltage control;
fLanguage :
English
Journal_Title :
Power Delivery, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8977
Type :
jour
DOI :
10.1109/61.107266
Filename :
107266
Link To Document :
بازگشت