• DocumentCode
    1151290
  • Title

    A Field Method for Determining the Leading and Lagging Regulator in an Open-Delta Connection [includes discussion]

  • Author

    Lokay, H.E. ; Custard, R.L.

  • Author_Institution
    ASSOCIATE MEMBER AIEE, Westinghouse Electric Corporation, East Pittsburgh, Pa.
  • Volume
    73
  • Issue
    2
  • fYear
    1954
  • Abstract
    To make correct line-drop compensator settings on single-phase regulators connected open delta on a 3-phase 3-wire system, it is necessary to identify the units, commonly called leading or lagging units, in which the regulator current has been advanced or retarded by the open-delta connection. This paper describes a field method for making this identification, using only the standard regulator controls without the knowledge of phase identity or sequence and also without additional measuring or phasing equipment. The discussion includes mathematical analysis, curves, sample calculations, and laboratory analysis used in developing this method.
  • Keywords
    Associate members; Cables; Capacitance; Capacitors; Costs; Investments; Propagation losses; Regulators; Substations; Switches;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, Part III. Transactions of the American Institute of Electrical Engineers
  • Publisher
    ieee
  • ISSN
    0097-2460
  • Type

    jour

  • DOI
    10.1109/AIEEPAS.1954.4499020
  • Filename
    4499020