Title
Effect of Clearing Time on Synchronous Machine Transient Stability
Author
Shackshaft, G. ; Aldred, A.S.
Volume
76
Issue
3
fYear
1957
fDate
4/1/1957 12:00:00 AM
Firstpage
633
Lastpage
637
Abstract
The paper is concerned with the effect of clearing time on the transient stability of a 2-machine system. An equivalent electronic analog interconnection for the equations of the system is used for the solution of the problem. The analog is based on a modified form of Park´s equations and it allows for the variation of field flux linkage with time during a transient disturbance. Results of a sample problem show boundaries of stability as functions of clearing time for different positions of a 3-phase earth fault.
Keywords
Circuit faults; Couplings; Equations; Integrated circuit interconnections; Power system interconnection; Power system stability; Power system transients; Power transmission lines; Synchronous machines; Voltage;
fLanguage
English
Journal_Title
Power Apparatus and Systems, Part III. Transactions of the American Institute of Electrical Engineers
Publisher
ieee
ISSN
0097-2460
Type
jour
DOI
10.1109/AIEEPAS.1957.4499626
Filename
4499626
Link To Document