• DocumentCode
    1170212
  • Title

    Reactive Power Dispatching for Power System Voltage Security

  • Author

    Palmer, R.E. ; Burchett, R.C. ; Happ, H.H. ; Vierath, D.R.

  • Author_Institution
    Philadelphia Electric Company
  • Issue
    12
  • fYear
    1983
  • Firstpage
    3905
  • Lastpage
    3909
  • Abstract
    An optimization-based method is presented for determining the scheduling of reactive equipment (capacitors for example) on an hourly basis for maximum steady-state power system security during normal and post-contingency conditions. The method simultaneously deals with the effects of a number of contingencies, and includes all bus voltages as constraints. The intended application is to schedule existing capacitors during periods of light load to prevent abnormally high voltages from occurring during normal and post-contingency condittons. Results from tests using a Pennsylvania-New Jersey-Maryland Interconnection (PJM) model are presented.
  • Keywords
    Capacitors; Costs; Dispatching; Fuels; Impedance; Power system planning; Power system security; Reactive power; Surges; Voltage;
  • fLanguage
    English
  • Journal_Title
    Power Apparatus and Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0018-9510
  • Type

    jour

  • DOI
    10.1109/TPAS.1983.317929
  • Filename
    4111918