Title :
Optimum Adjustment of Hydro Governors on Manitoba Hydro System
fDate :
4/1/1962 12:00:00 AM
Abstract :
This paper explains the methods used by Manitoba Hydro to establish optimum settings on governors at all plants on the Winnipeg River. The main criteria for stable governing as selected are that each machine will be stable when supplying an isolated load, and that the calculated speed transient following a small load change will be almost critically damped. Methods of finding the values of compensation and dashpot time, and how these factors are measured and checked in the field, are described.
Keywords :
Aging; Cities and towns; Cooling; Electrical equipment industry; Monitoring; Power generation; Rivers; System testing; Temperature control; Voltage;
Journal_Title :
Power Apparatus and Systems, Part III. Transactions of the American Institute of Electrical Engineers
DOI :
10.1109/AIEEPAS.1962.4501366