• DocumentCode
    1177896
  • Title

    A Flexible Unit Maintenance Scheduling Considering Uncertainties

  • Author

    Leou, R. C.

  • Author_Institution
    Yung Ta Institute of Technology and Commerce, Ping Tong, Taiwan
  • Volume
    21
  • Issue
    8
  • fYear
    2001
  • Firstpage
    60
  • Lastpage
    60
  • Abstract
    This paper presents a new methodology for maintenance scheduling that takes into account the uncertain constraints of the unit maintenance problem. If the spinning reserve is enough, this model can obtain an optimal solution based on reliability or cost concerned. Since the power development is more difficult than ever before, scheduling the unit maintenance under tight spinning reserve is a difficult task. In such a situation treating various constraints, such as the spinning reserve, duration of maintenance, the maintenance crew, etc., as soft constraints, a fuzzy 0-1 integer programming model is adopted to find the minimum violation solution. In order to verify that this model can be implemented in the real system, a case study of the Taiwan Power System is carried out using the algorithm.
  • Keywords
    Linear programming; Maintenance; Neural networks; Power system modeling; Power system relaying; Power transformers; Spinning; Substation protection; Uncertainty; Upper bound; 0-1 integer programming; Maintenance scheduling; crisp model; fuzzy model; spinning reserve;
  • fLanguage
    English
  • Journal_Title
    Power Engineering Review, IEEE
  • Publisher
    ieee
  • ISSN
    0272-1724
  • Type

    jour

  • DOI
    10.1109/MPER.2001.4311559
  • Filename
    4311559