Parameters required to maximize a thermoset hydro-generator stator winding life. Part II-monitoring, maintenance
Author :
Lyes, J.F. ; Goodeve, T. Earl ; Sedding, Howard
Author_Institution :
Ontario Hydro, Canada
Volume :
9
Issue :
3
fYear :
1994
fDate :
9/1/1994 12:00:00 AM
Firstpage :
628
Lastpage :
635
Abstract :
This paper describes the parameters required for a thermoset hydro-generator stator winding to achieve a service life of 50 years. Parameters covered are online monitoring and in-situ maintenance experience. These are the additional Ms of the DIM (design, installation, monitoring) rule
Keywords :
electric breakdown of solids; hydroelectric generators; insulation testing; life testing; machine insulation; machine testing; maintenance engineering; monitoring; stators; turbogenerators; DIM rule; experience; hydroelectric generators; in-situ maintenance; online monitoring; service; stator winding; testing; thermoset insulation life; Condition monitoring; Data analysis; Insulation testing; Partial discharges; Pattern recognition; Rotating machines; Samarium; Stator windings; Surface discharges; System testing;
fLanguage :
English
Journal_Title :
Energy Conversion, IEEE Transactions on
Publisher :
ieee
ISSN :
0885-8969
Type :
jour
DOI :
10.1109/60.326484
Filename :
326484
Link To Document :
بازگشت