• DocumentCode
    1211563
  • Title

    Accelerated trip scheme for second-zone distance protection

  • Author

    Sidhu, T.S. ; Ye, P. ; Sachdev, M.S.

  • Author_Institution
    Univ. of Western Ontario, Ont., Canada
  • Volume
    150
  • Issue
    3
  • fYear
    2003
  • fDate
    5/13/2003 12:00:00 AM
  • Firstpage
    325
  • Lastpage
    333
  • Abstract
    The theoretical aspects, design and testing of a new accelerated trip scheme for second-zone distance protection of HV/EHV transmission lines is described. The scheme is simple and provides relatively high-speed (60-70 ms) operation of the second-zone distance protection without requiring a communication channel. The scheme has been extensively tested using EMTDC simulations under various power system operating conditions. Simulation results show that the selectivity and speed of the proposed scheme are satisfactory for practical use in HV/EHV transmission line distance relays.
  • Keywords
    EMTP; digital simulation; power system simulation; power transmission lines; power transmission protection; relay protection; EMTDC simulations; HV/EHV transmission lines; accelerated trip scheme; distance protection selectivity; distance protection speed; distance relays; high-speed operation; power system operating conditions; second-zone distance protection;
  • fLanguage
    English
  • Journal_Title
    Generation, Transmission and Distribution, IEE Proceedings-
  • Publisher
    iet
  • ISSN
    1350-2360
  • Type

    jour

  • DOI
    10.1049/ip-gtd:20030197
  • Filename
    1201852