• DocumentCode
    1264132
  • Title

    Estimating restoration duration

  • Author

    Adibi, M.M. ; Milanicz, D.P.

  • Author_Institution
    IRD Corp., USA
  • Volume
    14
  • Issue
    4
  • fYear
    1999
  • fDate
    11/1/1999 12:00:00 AM
  • Firstpage
    1493
  • Lastpage
    1498
  • Abstract
    Restoration durations are typically estimated based on the availability of various prime mover types, sizes and numbers. In these estimates it is assumed that load can be picked up as soon as generation becomes available, and the time required for switching operation to energize transformers, energize lines and pickup loads is much less than the time required to make the generation available. In this paper, a case study is presented, supported by a field test, showing that the above assumptions may not necessarily be correct, and restoration duration should be estimated considering both the prime movers timings as well as the switching operations. The paper recommends that the restoration plans should be reviewed and broken down to its restoration levels, tasks and basic operating actions. Operating actions to include: opening/closing breakers, raising/lowering transformer taps, adjusting voltage and frequency set points, starting auxiliary motors, etc. Then, based on operators´ experience, the optimistic time, pessimistic time and the most likely time for each action be estimated and assigned. The overall restoration duration can then be estimated using the critical path method, which in turn may dictate revision of the overall restoration plan
  • Keywords
    critical path analysis; power system restoration; switching; auxiliary motors starting; basic operating actions; critical path method; frequency set points adjustment; most likely time; opening/closing breakers; optimistic time; pessimistic time; power system restoration; prime movers timings; raising/lowering transformer taps; restoration duration estimation; restoration levels; restoration plans; restoration tasks; switching operations; voltage set points adjustment; Customer service; Frequency; Meeting planning; Power system planning; Power system restoration; Power systems; Strategic planning; Testing; Timing; Transformers;
  • fLanguage
    English
  • Journal_Title
    Power Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8950
  • Type

    jour

  • DOI
    10.1109/59.801939
  • Filename
    801939