DocumentCode :
1277817
Title :
Transmission at 220 kv. on the Southern California Edison system: A symposium
Volume :
43
Issue :
11
fYear :
1924
Firstpage :
1025
Lastpage :
1026
Abstract :
Length of line was to be 275 miles. This was determined by the fact that the present Big Creek lines from Big Creek to Eagle Rock Substation are 243 miles in length and the lines from Eagle Rock to Laguna Bell Substation are 26 miles or a total length of 269 miles. Assuming that the future lines would terminate at Laguna Bell or in the same neighborhood, the round figure of 275 miles was used.
fLanguage :
English
Journal_Title :
A.I.E.E., Journal of the
Publisher :
ieee
ISSN :
0095-9804
Type :
jour
DOI :
10.1109/JAIEE.1924.6537783
Filename :
6537783
Link To Document :
بازگشت