Black-start and restoration of a part of the Italian HV network: modelling and simulation of a field test
Author :
Delfino, B. ; Denegri, G.B. ; Invernizzi, M. ; Morini, A. ; Bonini, E. Cima ; Marconato, R. ; Scarpellini, P.
Author_Institution :
Dept. of Electr. Eng., Genoa Univ., Italy
fDate :
8/1/1996 12:00:00 AM
Abstract :
ENEL (Italian Electricity Board) planned a set of operator guidelines for the restoration of parts of their national grid starting from selected hydroelectric power plants and progressively reaching thermal power generating units. In order to improve hydrothermal power system restoration reliability, ENEL periodically executes field tests taking advantage of the maintenance outages of the thermal groups. The paper concerns the modelling and simulation of an experimental test performed on the Italian W network near the French border. The study makes use of a stability code provided with user defined model facilities, enabling an accurate description of loads and regulation equipment during the restoration process
Keywords :
hydroelectric power stations; hydrothermal power systems; power system analysis computing; power system reliability; power system restoration; thermal power stations; ENEL; Italian HV network; computer simulation; field tests; hydroelectric power plants; hydrothermal power system restoration reliability; loads; maintenance outages; operator guidelines; regulation equipment; stability code; thermal power generating units; user defined model facilities; Guidelines; Hydroelectric power generation; Hydroelectric-thermal power generation; Maintenance; Mesh generation; Power generation; Power system modeling; Power system reliability; Power system restoration; System testing;
Journal_Title :
Power Systems, IEEE Transactions on