Abstract :
The long-term performance of BC hydro´s distribution network depends on the effectiveness of maintenance and capital replacement plans. These plans must not only identify short-term system requirements but also target expenditures to proactively address future performance issues in a cost-effective manner. This article describes the processes and tools used by BC Hydro Distribution Asset Strategy and Planning (DASP) to plan for the maintenance and replacement of existing assets. These processes focus on the development of long-term plans for maintaining safety and reliability, based on the ongoing maintenance requirements of distribution equipment as well as the anticipated end-of-life for BC Hydro´s aging asset base.
Keywords :
hydroelectric power stations; maintenance engineering; power distribution planning; BC hydro distribution asset maintenance; BC hydro distribution asset strategy and planning; BC hydro distribution network; DASP; capital replacement planning process; soccer field strategy; Asset management; Electricity supply industry; Hydroelectric power generation; Power distribution lines; Power system economics; Power system planning; Power system reliability;
fLanguage :
English
Journal_Title :
Power and Energy Magazine, IEEE
Publisher :
ieee
ISSN :
1540-7977
Type :
jour
DOI :
10.1109/MPE.2010.938517
Filename :
5618499
Link To Document :
بازگشت