Route selection and cable laying for the transatlantic cable system
Author
Jack, J.S. ; Leech, W.H. ; Lewis, H.A.
Volume
104
Issue
4
fYear
1957
fDate
1/1/1957 12:00:00 AM
Firstpage
109
Lastpage
121
Abstract
The repeatered submarine cables which form the backbone of the transatlantic telephone cable project were installed during the good weather periods of 1955 and 1956. The paper considers the factors entering into the selection of the routes, describes the planning and execution of the laying task, and presents a few observations on the human side of the venture. It also covers briefly the routing of some 55 nautical miles of repeatered submarine-type cable which were trenched in across the neck of the Burin Peninsula in Newfoundland to connect the Terrenceville submarine terminal with the cable station at Clarenville.
Keywords
cable laying; submarine cables; telephone lines; telephone networks;
fLanguage
English
Journal_Title
Proceedings of the IEE - Part B: Radio and Electronic Engineering
Publisher
iet
Type
jour
DOI
10.1049/pi-b-1.1957.0012
Filename
5243314
Link To Document