Abstract :
This paper describes how, in mid February of 1998, the Auckland central business district (New Zealand) suffered a power failure that left it with a minimal supply of power for three weeks and shortages and restrictions for another month or more. By the beginning of April, power supplies were sufficient-but still at risk from a single failure. It will be several months before the supply is reasonably secure and at least 18 months before a new tunnel carrying two 230 MVA 110 kV power cables is in service.
Keywords :
power system reliability; 110 kV; 230 MVA; Auckland central business district; New Zealand; power cables; power failure; power network reliability; power restrictions; power shortages; power supplies; project construction;
fLanguage :
English
Journal_Title :
Power Engineering Journal
Publisher :
iet
ISSN :
0950-3366
Type :
jour
DOI :
10.1049/pe:19980303
Filename :
693771
Link To Document :
بازگشت