DocumentCode
1399920
Title
Auckland central business district power failure
Author
Leyland, Bryan
Author_Institution
Leyland Consultants, Auckland, New Zealand
Volume
12
Issue
3
fYear
1998
fDate
6/1/1998 12:00:00 AM
Firstpage
109
Lastpage
114
Abstract
This paper describes how, in mid February of 1998, the Auckland central business district (New Zealand) suffered a power failure that left it with a minimal supply of power for three weeks and shortages and restrictions for another month or more. By the beginning of April, power supplies were sufficient-but still at risk from a single failure. It will be several months before the supply is reasonably secure and at least 18 months before a new tunnel carrying two 230 MVA 110 kV power cables is in service.
Keywords
power system reliability; 110 kV; 230 MVA; Auckland central business district; New Zealand; power cables; power failure; power network reliability; power restrictions; power shortages; power supplies; project construction;
fLanguage
English
Journal_Title
Power Engineering Journal
Publisher
iet
ISSN
0950-3366
Type
jour
DOI
10.1049/pe:19980303
Filename
693771
Link To Document