  • Title

    Development and trials of the 400 kV integral pipe-cooled cable system

  • Author

    Arnaud, U.C. ; Crockett, A.E. ; Burton, J. ; Nicholson, J.A.

  • Author_Institution
    Pirelli General Cable Works Ltd., Eastleigh, UK
  • Volume
    124
  • Issue
    3
  • fYear
    1977
  • fDate
    3/1/1977 12:00:00 AM
  • Firstpage
    286
  • Lastpage
    294
  • Abstract
    The need for reduction in wayleave requirements for cables for undergrounding of CEGB 400 kV very-heavy-duty lines has led to the development of the integral pipe-cooled cable system. The thermal design of the system is described and the various practical problems, pertaining to the installation of larger 400 kV cables in pipes, are outlined. Two field-trial installations have been constructed, the second being designed to resolve problems of cable movement which were not fully solved due to practical limitations in the first trial. The main results of both trials are reported. The applications, limitations and economic advantages of this cable system are briefly discussed.
  • Keywords
    cooling; economics; power cables; underground cables; 400 kV very heavy duty lines; economic advantages; field trials; installation; integral pipe cooled cable system; limitations; practical problems; thermal design; underground cables;
  • fLanguage
    English
  • Journal_Title
    Electrical Engineers, Proceedings of the Institution of
  • Publisher
    iet
  • ISSN
    0020-3270
  • Type

    jour

  • DOI
    10.1049/piee.1977.0056
  • Filename