    Assessment of Spare Transformer Requirements for Distribution Stations

  • Author

    Hamoud, Gomaa A.

  • Author_Institution
    Hydro One, Inc., Toronto, ON, Canada
  • Volume
    26
  • Issue
    1
  • fYear
    2011
  • Firstpage
    174
  • Lastpage
    180
  • Abstract
    This paper describes a probabilistic method for determining the number of spare transformers (regular spare transformers and mobile unit substations) required for a group of distribution transformers in order to meet a predetermined level of the group availability. The method is based on a Markov model and accounts for a number of factors that affect the number of spare units. The factors include the use of both regular spare transformers (RSTs) and mobile unit substations (MUSs), type of transformer failure and the various parameters of regular transformers, and spare transformers. Sensitivity analysis is performed to determine the factors that affect most the number of spare units. The proposed method is illustrated using a sample system of the Hydro One´s distribution stations.
  • Keywords
    Markov processes; distribution networks; power transformers; reliability; sensitivity analysis; substations; Markov model; distribution transformers; hydro one distribution stations; mobile unit substations; probabilistic method; regular spare transformers; sensitivity analysis; transformer failure; Deployment time for mobile unit substation; Markov model; distribution station; minor and major transformer failures; mobile unit substation; regular spare transformer; sensitivity analysis; system availability; transformer failure rate;
  • fLanguage
    English
  • Journal_Title
    Power Systems, IEEE Transactions on
  • Publisher
    ieee
  • ISSN
    0885-8950
  • Type

    jour

  • DOI
    10.1109/TPWRS.2010.2046429