Title :
Matching mcnary electrical characteristics with Bonneville transmission system
Author :
Hoard, B. V. ; Weiner, Lewis
Author_Institution :
Bonneville Power Administration, Portland, Oreg.
Abstract :
Low-reactance powerhouse equipment would increase costs for the McNary Dam installation by $3,200,000. Combining cost analysis with network analyzer studies, however, showed that this increase would be more than offset by transmission-line savings. Over-all savings of $7,000,000 are estimated.
Keywords :
Generators; Loading; Power system stability; Reactive power; Stability analysis; Transient analysis;