An efficient method for optimal scheduling of fixed head hydro and thermal plants
Author
Rashid, Abdul Halim Abdul ; Nor, Khalid Mohamed
Author_Institution
Malaya Univ., Kuala Lumpur, Malaysia
Volume
6
Issue
2
fYear
1991
fDate
5/1/1991 12:00:00 AM
Firstpage
632
Lastpage
636
Abstract
An efficient and optimal method for scheduling thermal plants in coordination with fixed-head hydro units is presented. The method linearizes the coordination equation and solves for the water availability constraint separately from unit generation. Once the water constraint Lagrange multiplier is determined, the unit output can be computed easily. Case studies with various systems are presented and discussed
Keywords
hydroelectric power stations; scheduling; thermal power stations; Lagrange multiplier; coordination equation; fixed head hydro; optimal scheduling; thermal plants; water availability constraint; Availability; Cost function; Equations; Jacobian matrices; Lagrangian functions; Optimal scheduling; Partial discharges; Power generation; Processor scheduling; Propagation losses;
fLanguage
English
Journal_Title
Power Systems, IEEE Transactions on
Publisher
ieee
ISSN
0885-8950
Type
jour
DOI
10.1109/59.76706
Filename
76706
Link To Document