Abstract
This paper presents a novel economic dispatch strategy for a generation company which owns several units with different fuel costs, efficiency, and locations, and has a bilateral contract with several large customers. The proposed strategy not only considers the generation cost, but also takes into account the wheeling charge for the use of the transmission system. A modified megawatt-mile method is proposed to calculate the wheeling cost in this paper. Finally, the calculation results of economic dispatch for a generation company with two units and their loads in a real power system is demonstrated
Keywords
costing; power generation dispatch; power generation economics; power transmission economics; bilateral contract; economic dispatch; efficiency; fuel costs; generation company; generation cost; locations; modified megawatt-mile method; pricing model; real power system; transmission service charge; transmission system; wheeling charge; Contracts; Cost function; Environmental economics; Fuel economy; Job shop scheduling; Monopoly; Power generation; Power generation economics; Power system economics; Power systems;
fLanguage
English
Journal_Title
Power Systems, IEEE Transactions on
Publisher
ieee
ISSN
0885-8950
Type
jour
DOI
10.1109/59.962420
Filename
962420
Link To Document