Abstract :
As a result of availability studies, comparing a traditional substation configuration with conventional equipment and an innovative solution with disconnecting circuit breakers, the latter was found drastically better with regard to power flow. The use of disconnecting circuit breakers also leads to a reduction of the total number of HV apparatus in the substation with associated reduction of space requirements and costs
Keywords :
circuit breakers; load flow; maintenance engineering; power system protection; power system reliability; substations; HV apparatus; availability studies; cost savings; disconnecting circuit breakers; power flow; reliability improvement; space requirements reduction; substation refurbishment;
fLanguage :
English
Publisher :
iet
Conference_Titel :
Electricity Distribution, 2001. Part 1: Contributions. CIRED. 16th International Conference and Exhibition on (IEE Conf. Publ No. 482)
Conference_Location :
Amsterdam
ISSN :
0537-9989
Print_ISBN :
0-85296-735-7
Type :
conf
DOI :
10.1049/cp:20010682
Filename :
942780
Link To Document :
بازگشت