Title :
Project scheduling with alternative technologies: Incorporating varying activity duration variability
Author :
Creemers, S. ; Leus, R. ; De Reyck, B.
Author_Institution :
Dept. of Decision Sci. & Inf. Manage., K.U. Leuven, Leuven, Belgium
fYear :
2010
fDate :
7-10 Dec. 2010
Firstpage :
641
Lastpage :
645
Abstract :
We look into project scheduling with expected-NPV objective and stochastic activity durations. Individual activities carry a risk of failure, and an activity´s failure can cause the overall project to fail. More than one alternative may exist for reaching intermediate project deliverables, and these alternatives can be implemented either in parallel or sequentially. In this paper, optimal solutions to the scheduling problem are found by means of stochastic dynamic programming. We examine the impact of the variability of activity durations on the project´s value. We also illustrate that higher operational variability does not always lead to lower project values, meaning that (sometimes costly) variance-reduction strategies are not always advisable.
Keywords :
dynamic programming; project management; research and development management; scheduling; stochastic programming; expected-NPV objective; net present value; project scheduling; stochastic activity durations; stochastic dynamic programming; varying activity duration variability; Job shop scheduling; Markov processes; Nickel; Optimization; Product development; Uncertainty; alternative technologies; net present value; project scheduling; stochastic activity durations; uncertainty;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Industrial Engineering and Engineering Management (IEEM), 2010 IEEE International Conference on
Conference_Location :
Macao
ISSN :
2157-3611
Print_ISBN :
978-1-4244-8501-7
Electronic_ISBN :
2157-3611
Type :
conf
DOI :
10.1109/IEEM.2010.5674523
Filename :
5674523
Link To Document :
بازگشت