Abstract :
Partial discharge measurement is a kind of effective condition check method for high power transformer. Normally, when a high power transformer needs to be checked by partial discharge measurement periodically, outage is required. Here, a newly developed measurement method for transformer is introduced in which a new kind of capacitive coupling sensor is applied. The sensor consists of a pair of metal plates and a high frequency CT, which can be installed at the flange of the high voltage bushing of the transformer during the transformer in commercial service operation, without any outage.
Keywords :
bushings; capacitive sensors; partial discharge measurement; power transformers; capacitive coupling sensor; check method; high power transformer; high voltage bushing; metal plates; partial discharge measurement; service operation; Capacitive sensors; Capacitors; Frequency; Insulators; Partial discharge measurement; Partial discharges; Power measurement; Power transformer insulation; Power transformers; Pulse transformers; PDM sensor; bushing; capacitive coupling; high frequency CT (HFCT); outage; partial discharge (PD); partial discharge measurement (PDM); pulse current; transformer;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Condition Monitoring and Diagnosis, 2008. CMD 2008. International Conference on
Conference_Location :
Beijing
Print_ISBN :
978-1-4244-1621-9
Electronic_ISBN :
978-1-4244-1622-6
Type :
conf
DOI :
10.1109/CMD.2008.4580436
Filename :
4580436
Link To Document :
بازگشت