NPD project schedules-great works of fiction
Author
Ledwith, A. ; Callaghan, S. H O
Author_Institution
Dept. of Manuf. & Operations Eng., Limerick Univ., Ireland
Volume
2
fYear
2002
fDate
2002
Firstpage
767
Abstract
This paper presents the results of a study of the planning and scheduling of NPD projects within five high technology firms. The ability of these firms to release new products according to schedule and also the most common reasons for missing schedule deadlines are examined. Particular attention is paid to the scheduling of NPD projects and the application of formal project scheduling techniques. Initial results suggest that traditional project scheduling tools and techniques are not adequate when scheduling high-risk, high-technology projects. Project managers typically do not plan accurately and fail to anticipate changing customer requirements resulting in consistently over optimistic delivery dates. A discussion on whether NPD projects are delivered behind schedule because original schedules are inaccurate or because of poor project management helps to clarify the situation.
Keywords
product development; project management; research and development management; scheduling; NPD projects; customer requirements; high technology firms; high-risk high-technology projects; new product development schedules; project managers; project scheduling techniques; schedule deadlines; Acceleration; Costs; Finishing; Job shop scheduling; Knowledge management; Product development; Project management; Pulp manufacturing; Technology planning; Uncertainty;
fLanguage
English
Publisher
ieee
Conference_Titel
Engineering Management Conference, 2002. IEMC '02. 2002 IEEE International
Print_ISBN
0-7803-7385-5
Type
conf
DOI
10.1109/IEMC.2002.1038534
Filename
1038534
Link To Document