This paper develops a risk constrained expected profit maximization model for a generating station operating under Availability Based Tariff (ABT) regime in India. The decision strategy of the generator is to optimize the availability target trajectory for a yearly time span in appropriate time intervals. The model considers stochastic behaviour of generating units´ outage, Unscheduled Interchange (UI) and load Schedule and the other deterministic constraints occurring in the yearly time horizon. Stochastic programming framework is applied to estimate the optimal annual availability target for expected annual profit maximization. The profit verses risk trade off is achieved by constraining the objective function with Conditional Value at Risk (CVaR). A numerical example of a generating station is illustrated to show the revenue maximization strategy by this optimization.
Keywords :
optimisation; power system economics; power system planning; tariffs; Genco; India; annual profit maximization; decision strategy; deterministic constraints; generating station; generating unit outage; load schedule; revenue maximization; risk constrained operation planning; stochastic programming; tariff regime; unscheduled interchange; Availability Based Tariff; CVaR; Monte Carlo Simulation; Stochastic Programming;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Power and Energy Society General Meeting, 2010 IEEE
Conference_Location :
Minneapolis, MN
ISSN :
1944-9925
Print_ISBN :
978-1-4244-6549-1
Electronic_ISBN :
1944-9925
Type :
conf
DOI :
10.1109/PES.2010.5589392
Filename :
5589392
Link To Document :
بازگشت