  • Title

    Validation of battery energy storage control for wind farm dispatching

  • Author

    Teleke, Sercan ; Baran, Mesut E. ; Bhattacharya, Subhashish ; Huang, Alex

  • Author_Institution
    Quanta Technol., Raleigh, NC, USA
  • fYear
    2010
  • fDate
    25-29 July 2010
  • Firstpage
    1
  • Lastpage
    7
  • Abstract
    Integrating a Battery Energy Storage System (BESS) with a large wind farm can smooth out the intermittent power from the wind farm. This paper focuses on the experimental validation of the proposed control strategy for the BESS. The paper considers a rule based control scheme, which is the solution of the optimal control problem defined, to incorporate the operating constraints of the BESS, such as state of charge limits, charge/discharge current limits and lifetime. The goal of the control is to have the BESS provide as much smoothing as possible so that the wind farm can be dispatched on an hourly basis based on the forecasted wind conditions. The effectiveness of this control strategy has been tested by using an actual wind farm data and it is shown that optimal dispatching is achieved with the proposed method. Finally, the method is verified with an experiment and the details of the implementation are explained.
  • Keywords
    energy storage; power control; power generation dispatch; wind power plants; battery energy storage control; optimal control problem; wind farm dispatching; Battery energy storage system (BESS); closed loop optimal control; dispatchability; rule based control; wind energy;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Power and Energy Society General Meeting, 2010 IEEE
  • Conference_Location
    Minneapolis, MN
  • ISSN
    1944-9925
  • Print_ISBN
    978-1-4244-6549-1
  • Electronic_ISBN
    1944-9925
  • Type

    conf

  • DOI
    10.1109/PES.2010.5589640
  • Filename
    5589640