Title
Implementation of UCA/IEC 61850 for Substation Automation in Grant County Public Utility District
Author
White, Joseph
Author_Institution
Grant County Public Utility District, Ephrata, WA
fYear
2006
fDate
21-24 May 2006
Firstpage
384
Lastpage
389
Abstract
Grant County Public Utility District (The District) is a consumer owned utility in central Washington State that initiated a substation modernization program beginning in 2001. In order to minimize the risk associated with introducing modern substation automation technology into this utility, the District undertook a detailed investigation of two different approaches in order to determine which technologies would serve their needs best. These approaches included the evaluation of DNP and UCA technology. The District first evaluated these technologies in a lab environment using a variety of devices and then installed devices in the first substation as a pilot. The paper described the motivation for the project, the testing that was done, and the pilot implementation. The paper also presents the results of these activities and includes a description of the plan that were implemented to deploy IEC 61850 across the system in the future
Keywords
IEC standards; SCADA systems; electricity supply industry; substation automation; Grant County Public Utility District; UCA/IEC 61850; central Washington State; substation automation; substation modernization program; Control systems; Hardware; IEC standards; Optical fiber communication; Power systems; Protocols; SCADA systems; Substation automation; Switches; Testing;
fLanguage
English
Publisher
ieee
Conference_Titel
Transmission and Distribution Conference and Exhibition, 2005/2006 IEEE PES
Conference_Location
Dallas, TX
Print_ISBN
0-7803-9194-2
Type
conf
DOI
10.1109/TDC.2006.1668523
Filename
1668523
Link To Document