    Calculating critical degree of the path in a project network with fuzzy activity duration

  • Author

    Hongxiang Ouyang ; Yinghui Jian

  • Author_Institution
    Bus. Sch., Hohai Univ., Nanjing, China
  • fYear
    2011
  • fDate
    8-11 Jan. 2011
  • Firstpage
    86
  • Lastpage
    88
  • Abstract
    In traditional CPM/PERT technique, activity duration must be represented either as crisp number or as random variable drawn from certain probability distribution. However, it is usually difficult to define and estimate precisely the operation time for each activity in a real situation. Based on the liner programming and Zadeh´s extension principle, this paper presents a method for measuring critical degree of the path in a project network with fuzzy activity times. In the last, this paper uses matlab language to program, and verifies its feasibility and simplicity by an example.
  • Keywords
    PERT; critical path analysis; fuzzy set theory; linear programming; statistical distributions; CPM; PERT; Zadeh extension principle; critical path method; fuzzy activity duration; linear programming; matlab language; probability distribution; Educational institutions; Indexes; Mathematical model; Operations research; Probability distribution; Programming; critical path; fuzzy PERT; project management;
  • fLanguage
    English
  • Publisher
    ieee
  • Conference_Titel
    Management Science and Industrial Engineering (MSIE), 2011 International Conference on
  • Conference_Location
    Harbin
  • Print_ISBN
    978-1-4244-8383-9
  • Type

    conf

  • DOI
    10.1109/MSIE.2011.5707528
  • Filename
    5707528