DocumentCode
2478419
Title
Smart Grid using 1st generation AMR meters — An operational view
Author
Lindmark, Jenny ; Hakansson, Mats
Author_Institution
Malarenergi Elnat AB, Sweden
fYear
213
fDate
10-13 June 213
Firstpage
1
Lastpage
4
Abstract
This paper describes how the DSO Malarenergi Elnät AB has used their 1St generation smart AMR meters to control the LV network. Due to the early meter regulation in Sweden, Mälarenergi bought their AMR meters in 2006. To fully take advantage of the 1st generation smart meter functionality to control the LV network, Malarenergi started a project to connect the DMS system with the AMR meters. The benefit is that the control room can monitor the whole operational chain from Substation to customer. This results in better customer service, faster handling, localization and restoration of faults in LV network. The project has also given many valuable experiences regarding possibilities as well as limitations in the existing AMI solution. This will be useful input for Mälarenergi when specifying the requirements for 2nd generation smart meters and AMI solution.
Keywords
power system measurement; smart meters; smart power grids; AMI solution; DMS system; DSO Malarenergi Elnät AB; LV network control; Sweden; advanced metering infrastructure solution; automatic meter reading; control room; customer service; distribution management system; fault restoration; first generation smart AMR meters; smart grid; substation;
fLanguage
English
Publisher
iet
Conference_Titel
Electricity Distribution (CIRED 2013), 22nd International Conference and Exhibition on
Conference_Location
Stockholm
Electronic_ISBN
978-1-84919-732-8
Type
conf
DOI
10.1049/cp.2013.1136
Filename
6683739
Link To Document