The European Union ITER Home Team analysed the possibility of feeding ITER directly from the 400 kV grid. The study was based on the assumption that ITER will be located on the sites where the 400 kV grid feeds fusion experiments in Europe at present, and was performed in cooperation with the Electric Companies concerned. This study shows, as a first approximation, the ability of the European Grid to supply the ITER load, provided that measures such as increasing the power reserve and providing reactive power compensation are taken as the site location demands
Keywords :
Tokamak devices; fusion reactor design; fusion reactors; power supplies to apparatus; 400 kV; European Grid; ITER load; power reserve; reactive power compensation; site location demands; Circuits; Energy measurement; Europe; Feeds; Laboratories; Performance evaluation; Power generation; Pulsed power supplies; Reactive power; Voltage;
Conference_Titel :
Fusion Engineering, 1995. SOFE '95. Seeking a New Energy Era., 16th IEEE/NPSS Symposium
Conference_Location :
Champaign, IL
Print_ISBN :
0-7803-2969-4
DOI :
10.1109/FUSION.1995.534197