Calculation method of delay claims with multi-event interference based on shapley value
Author
Cui, Dong-hong ; Yao, Li
Author_Institution
Dept. of Manage., Shenyang Univ. of Technol., Shenyang, China
fYear
2009
fDate
21-23 Oct. 2009
Firstpage
420
Lastpage
423
Abstract
As an important measure for parties of the contract to protect their own interests, project claim is the core of project contract management. For claims of time delay under multi-agent and multi-event interference, it is difficult to assess the responsibility. To solve this problem, this paper presents a new analytical method based on Shapley value, and brings forward a new parameter called Correction Factor to denote the affecting degree of every interference event. On the basis of this method, project delay responsibility is allotted to each single responsible activity, and then allotted to both owner and contractor in each single responsible activity. Finally, the responsibility is reallotted to the responsible parties through Correction Factor. This method takes into account the impact of the interference event, and makes the responsibility-sharing more equitable.
Keywords
contracts; project management; Shapley value; correction factor; multiagent interference; multievent interference; project claim; project contract management; project delay responsibility; responsibility-sharing; time delay claim; Delay effects; Forward contracts; Game theory; Interference; Large-scale systems; Process planning; Project management; Protection; Technology management; Uncertainty; Correction Factor; Responsibility-sharing; Shapely value;
fLanguage
English
Publisher
ieee
Conference_Titel
Industrial Engineering and Engineering Management, 2009. IE&EM '09. 16th International Conference on
Conference_Location
Beijing
Print_ISBN
978-1-4244-3671-2
Electronic_ISBN
978-1-4244-3672-9
Type
conf
DOI
10.1109/ICIEEM.2009.5344560
Filename
5344560
Link To Document