Transformer overvoltage problems and countermeasures at black start
Author :
Funakoshi, Takahiko ; Furukawa, Koichiro ; Kawachino, Toshihiro ; Takasaki, Shinji ; Shimojo, Toshikazu ; Hirayama, Kaiichirou ; Sogabe, Toshiaki ; Shimamura, Takeo ; Hashimoto, Hidetoshi ; Nohara, Shinichi
Author_Institution :
Kyushu Electr. Power Co. Inc., Japan
Volume :
2
fYear :
2003
fDate :
13-17 July 2003
Abstract :
A system of Kyushu Electric Power Company Inc. or KEPCO (about 19 GW) belongs to the western Japan system (110 GW) and has a 500-kV and 220-kV transmission line in a loop configuration. Japan´s power system has high reliability and experienced no blackout for the past several decades. However, there is a possibility, though very slight, of a blackout in the event of a big earthquake or unforeseen accident. Considering the risk of blackout, KEPCO has been conducting studies on system restoration. This paper discusses a mechanism of an overvoltage phenomenon during a restoration period in which, about 0.2 seconds or more after a transformer is energized, a voltage becomes maximum in excess of 200% of the rated voltage. The paper also discusses countermeasures against this phenomenon.
Keywords :
magnetic flux; overvoltage; power system restoration; power transformers; power transmission lines; 110 GW; 220 kV; 500 kV; Japan; flux saturation; power supply blackout; power system restoration; transformer overvoltage problem; transmission line; Circuit faults; Mesh generation; Power generation; Power system modeling; Power system reliability; Power system restoration; Power transformer insulation; Power transmission; Power transmission lines; Voltage control;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Power Engineering Society General Meeting, 2003, IEEE
Print_ISBN :
0-7803-7989-6
Type :
conf
DOI :
10.1109/PES.2003.1270363
Filename :
1270363
Link To Document :
بازگشت