• DocumentCode
    276479
  • Title

    Computerized control on 11 kV distribution network of the Hongkong Electric Co. Ltd

  • Author

    Wan, W.K.

  • Author_Institution
    Hongkong Electr. Co. Ltd., Hong Kong
  • fYear
    1991
  • fDate
    5-8 Nov 1991
  • Firstpage
    527
  • Abstract
    The author examines the development, operational experience, and future prospect of computerised control on the 11 kV distribution network of the Hongkong Electric Co. Ltd. (HEC). Computerized control proves to be successful in saving human efforts in carrying out switching manually at substations. Apart from saving time required for switching, it is also a safer means of switching. It also reduces the supply interruption time to an acceptable level in the event of a 11 kV cable fault and can be seen as an economical alternative to a full ring 11 kV network installed with unit protection
  • Keywords
    distribution networks; electrical faults; power system computer control; substations; switching; 11 kV; Hongkong Electric Company; cable fault; computerised control; distribution network; substations; supply interruption time; switching;
  • fLanguage
    English
  • Publisher
    iet
  • Conference_Titel
    Advances in Power System Control, Operation and Management, 1991. APSCOM-91., 1991 International Conference on
  • Conference_Location
    IET
  • Print_ISBN
    0-86341-246-7
  • Type

    conf

  • Filename
    154129