Title :
Use of system costing for energy exchange
Author_Institution :
Imperial Coll., London, UK
Abstract :
In setting up energy and capacity exchange contracts, the cost of using the system to effect the exchange must be estimated. This cost will depend upon at least two factors, namely: cost of losses and system operating cost (per MWh); and system infrastructure cost to pay for plant and any necessary reinforcement (per MW). The problem then is to allocate a charge for use-of-system which is seen to be fairly divided between fixed and variable costs. This is not unlike charging for a power supply to any customer
Keywords :
economics; power system interconnection; economics; energy exchange; infrastructure cost; losses; operating cost; system costing;
Conference_Titel :
System Interconnection and Energy Exchange Across National Boundaries, IEE Colloquium on
Conference_Location :
London