An active plan based critical chain method
Author
Ming, Chen ; Wuliang, Peng
Author_Institution
Modern Educ. Technol. Center, Shenyang Ligong Univ., Shenyang, China
fYear
2009
fDate
17-19 June 2009
Firstpage
2765
Lastpage
2769
Abstract
For some projects, to void the risk of project delay, the all the tasks should be finished as soon as possible. However, the critical chain method (CCM) requires the non critical tasks to be executed as late as possible. Therefore, adopting the merits of CCM and improving it to schedule project tasks as early as possible is a meaningful work. In this paper, a new critical chain method called active plan based critical chain method is presented. Other than the old one, the new CCM is created based on the active plan, that is, all tasks should be executed as early as possible. And then, the schedule scheme of active plan based critical chain method is given, including searching critical chain, no critical chain and setting buffers. By a project case, the schedule scheme is illustrated, and the effectiveness of the schedule scheme is verified.
Keywords
critical path analysis; production planning; active plan schedule scheme; critical chain method; early tasks executed; no critical chain method; project delay risks void; project management; project tasks improvement; searching critical chain method; setting buffers method; Art; Constraint theory; Delay; Educational technology; Processor scheduling; Product design; Production; Project management; Resource management; Risk management; critical chain method; planning and scheduling; project management;
fLanguage
English
Publisher
ieee
Conference_Titel
Control and Decision Conference, 2009. CCDC '09. Chinese
Conference_Location
Guilin
Print_ISBN
978-1-4244-2722-2
Electronic_ISBN
978-1-4244-2723-9
Type
conf
DOI
10.1109/CCDC.2009.5194975
Filename
5194975
Link To Document