DocumentCode :
2973541
Title :
An industrial application of resource constrained scheduling for quick changeover
Author :
Sousa, R.M. ; Lima, R.M. ; Carvalho, J.D. ; Alves, A.C.
Author_Institution :
Dept. of Production & Syst., Univ. of Minho, Guimaraes, Portugal
fYear :
2009
fDate :
8-11 Dec. 2009
Firstpage :
189
Lastpage :
193
Abstract :
This paper describes the improvement of the quick changeover process of a painting line in a wooden frames factory. The well-known SMED technique (single minute exchange of die) was applied. However the characteristics of the setup operations (those characteristics also occur in other industrial changeover scenarios) have revealed the possibility of advantageous utilization of resource constrained project scheduling methods. The application of one of these methods represents an innovative contribution to the quick changeover area, allowing (when applicable) the scheduling of the involved setup operations, considering their duration, precedence relations and resources´ need, in order to achieve a reduced setup time.
Keywords :
constraint theory; painting; project management; resource allocation; scheduling; wood processing; industrial application; painting line; quick changeover process; resource constrained project scheduling methods; resource constrained scheduling; single minute exchange of die technique; wooden frames factory; Assembly; Industrial relations; Job shop scheduling; Mass production; Painting; Production facilities; Production systems; Scheduling algorithm; Time factors; Wood industry; Brooks´ algorithm; SMED; quick changeover; resource constrained scheduling; setup time;
fLanguage :
English
Publisher :
ieee
Conference_Titel :
Industrial Engineering and Engineering Management, 2009. IEEM 2009. IEEE International Conference on
Conference_Location :
Hong Kong
Print_ISBN :
978-1-4244-4869-2
Electronic_ISBN :
978-1-4244-4870-8
Type :
conf
DOI :
10.1109/IEEM.2009.5373391
Filename :
5373391
Link To Document :
بازگشت