Abstract :
This paper presents the electric diagram conception of the new substation BH Centro 2, which will substitute the existent substation BH Centro 1, that currently supplies the central area of Belo Horizonte city. The BH Centro 1 substation is the biggest substation of Cemig Distribution Company, with regard to its transformation capacity (138-13.8 kV - 150 MVA). Operating since 1970, the substation has been showing maintenance problems associates to the difficulty of attainment of spare parts for some equipment and rise of the risk of failure due to its high period of operation. Thus, the construction of a new substation was defined. The conception of the BH Centro 2 substation faced some challenges, due limitations of space, special operational requirements because of medium voltage networks characteristics and short-circuits level limitation. Besides, we tried to avoid the utilization of special equipments, like high impedance transformers and high capacity reactors.
Keywords :
maintenance engineering; risk management; short-circuit currents; substations; BH Centro 2- Belo Horizonte Minas Gerais; Brazil; Cemig distribution company; electric diagram conception; high capacity reactors; impedance transformers; maintenance problems; substation; voltage 138 kV to 13.8 kV; voltage networks; Impedance; Inductors; Loading; Low voltage; Medium voltage; Substations; Sulfur hexafluoride; Electric Diagram; Planning; Short circuit limitation; Substation; Underground Network;
Conference_Titel :
Transmission and Distribution Conference and Exposition: Latin America (T&D-LA), 2010 IEEE/PES
Conference_Location :
Sao Paulo
Print_ISBN :
978-1-4577-0488-8
DOI :
10.1109/TDC-LA.2010.5762954